BARREL Digital Exchange
Bharat Atom Renewable Resources Energy Limited
SAMPLE — illustrative data
Ref. XR-26-0401
03 November 2026
Prequalification Report
Illustrative Solar EPC Pvt Ltd — solar EPC up to 50 MW AC, 33 kV (sample)
- Exchange
- Contractor Registry
- Prepared for
- Sample Energy Ventures Pvt Ltd (illustrative)
- Prepared by
- BARREL Digital Exchange desk
1.Legal entity (as declared)
- Legal name
- Illustrative Solar EPC Pvt Ltd
- Entity type
- Private limited company, incorporated 2016
- Registered office
- Jodhpur district, Rajasthan
- Operating offices
- Ahmedabad district, Gujarat; Bhopal district, Madhya Pradesh
- Registration identifiers
- GSTIN and CIN recorded on file; numbers withheld in this sample
- Authorised signatory
- One director; authority letter dated 14 October 2026 on file
2.Registrations and licences held
- Electrical contractor licence, Rajasthan
- Class A; valid to 31 December 2027; checked
- Electrical contractor licence, Gujarat
- Class A; valid to 31 March 2027; checked, renewal due
- Electrical contractor licence, Madhya Pradesh
- Application pending (as declared); not checked
- Labour and provident fund registrations
- Recorded on file; checked
- Tax registrations
- Recorded on file; checked
3.Work categories, voltage classes and capacity bands
- Work categories
- Solar EPC (ground-mounted); 33 kV switchyard and evacuation line; civil and mounting-structure works
- Voltage class
- Up to 33 kV (one 66 kV bay as a subcontractor, self-declared)
- Capacity band
- 5–50 MW AC per project
- Completed capacity
- 212 MW across 9 projects since 2018 (as declared); 145 MW is covered by the references below
- Geography
- Rajasthan, Gujarat, Madhya Pradesh
4.Manpower, equipment and turnover (as declared)
- Own staff
- 140, including 26 engineers and 9 safety officers
- Site workforce
- Up to 600 through registered subcontractors
- Key equipment
- 4 pile-driving rigs, 2 hydraulic cranes (25 t), 6 tractor-trailers, 3 cable-laying sets, 2 relay test kits
- Turnover band
- ₹100–250 crore in each of the last three financial years
- Financial statements
- Audited statements for three years uploaded; not reviewed by BARREL
5.Safety record (as declared)
The contractor reports no fatality and two lost-time incidents across all sites in the last three years, a safety management system certified to an international standard, and monthly safety audits at every site. BARREL has seen the certificate and the incident log summary; it has not visited any site.
6.Project references
| Project | Client | Capacity | Year | Reference check |
|---|---|---|---|---|
| 50 MW solar plant with 33 kV evacuation, Jodhpur district, Rajasthan | Illustrative Renewables Ltd | 50 MW AC | 2024 | Confirmed by client, 30 October 2026 |
| 40 MW solar plant, Kutch district, Gujarat | Sample Power Developers LLP (illustrative) | 40 MW AC | 2023 | Confirmed by client, 02 November 2026 |
| 30 MW solar plant, Neemuch district, Madhya Pradesh | Illustrative Industrial Park Co. | 30 MW AC | 2025 | Awaiting client reply |
| 25 MW captive solar plant, Banaskantha district, Gujarat | Sample Captive Energy Pvt Ltd (illustrative) | 25 MW AC | 2022 | Not checked; client declined contact |
7.Certificates and expiry dates
| Certificate | Valid to | Status on report date |
|---|---|---|
| Quality management system certificate | 31 August 2027 | Current; copy checked |
| Occupational health and safety certificate | 31 August 2027 | Current; copy checked |
| Public liability insurance | 31 March 2027 | Current; renewal alert set |
| Workmen's compensation insurance | 31 March 2027 | Current; renewal alert set |
| Contractor all-risk insurance | Per project | Not held at registry level |
8.Verification record and prequalification outcome
Illustrative outcome: prequalified, conditional, for solar EPC packages up to 50 MW AC at 33 kV in Rajasthan and Gujarat, with Madhya Pradesh subject to the pending state licence and the open reference. Conditions: renewal of the Gujarat licence before 31 March 2027 and confirmation of the Neemuch reference. This is BARREL's indicative assessment for the buyer's own decision; it is not an award, a certification or a guarantee of performance.
- Entity documents
- Checked 28 October 2026
- Licences and certificates
- Checked 29 October 2026 against copies and public records where available
- Project references
- 2 of 4 confirmed by 02 November 2026; 1 awaiting reply; 1 not checked
- Label shown on profile
- Reference checked
- Reviewed by
- BARREL verification analyst, with a second review by the exchange manager