SAMPLE

XL-26-0101 · Asset sale mandate

25 MW AC operating solar plant with utility PPA — sale mandate

Jodhpur district, Rajasthan

Ground-mounted solar plant of 25 MW AC / 32.5 MWp DC, in operation since March 2019 under a 25-year PPA with a state distribution utility (about 17 years remaining). The seller offers 100% of the single-asset SPV, with the existing term debt to be assumed or refinanced by the buyer.

Seller
Sample Solar Assets SPV Pvt Ltd (illustrative)
Capacity
25 MW AC / 32.5 MWp DC, crystalline PV, fixed tilt
COD
March 2019
Offtake
25-year PPA with a state distribution utility, ₹3.14 per kWh fixed
Land
120 acres on a 29-year lease from 2018 (21 years remaining)
Generation FY 2025-26
58.4 GWh exported (CUF 20.5% on DC)
Asking range
₹118–132 crore enterprise value (indicative)
BARREL reviewedThe listing was reviewed for completeness and the checks shown in its verification record. This is not a warranty or guarantee.

Status: Live

SAMPLE

XL-26-0102 · Minority / majority stake enquiry

50 MW wind + 20 MWh BESS hybrid under development — majority partner sought

Kutch district, Gujarat

Wind-plus-storage project at an advanced development stage: twelve months of mast data, about 60% of the land under agreement and a connectivity application filed. The developer seeks a majority equity partner to fund construction and would stay on as minority holder and O&M partner.

Developer
Illustrative Wind Co. (illustrative)
Configuration
50 MW wind (3 MW-class turbines) + 10 MW / 20 MWh lithium-ion BESS
Stage
Development; about 250 acres required, 150 under agreement; target COD Q4 2028
Wind resource
12 months of mast data; P50 CUF 34% (developer's consultant)
Connectivity
Application filed for a 66 kV bay at a state substation; grant awaited
Offtake
No PPA yet; targeting a hybrid tender or a commercial buyer
Stake offered
51–74% equity against construction funding
Documents checkedSpecified organisation documents were reviewed on the stated date. This is not a guarantee of solvency or performance.

Status: Under due diligence

SAMPLE

XL-26-0103 · SPV sale

SPV sale — private limited company holding a 10 MW AC solar plant

Solapur district, Maharashtra

Sale of 100% of the shares of a single-asset private limited company. The plant, 10 MW AC / 13 MWp DC, has supplied a commercial consumer under an open-access PPA since 2021. Term debt of ₹28 crore was to be assumed or refinanced by the buyer. Shown as a closed sample.

Seller
Example Renewables Holdings Pvt Ltd (illustrative)
Capacity
10 MW AC / 13 MWp DC
COD
September 2021
Offtake
15-year open-access PPA with a commercial consumer (about 10 years remaining)
Land
48 acres held by the SPV (seller-declared)
Debt
Term loan of ₹28 crore outstanding
Asking range
₹16–22 crore equity value (indicative), plus debt
Self-declaredInformation was provided by the listing owner and has not been independently verified.

Status: Closed — sample

SAMPLE

XL-26-0104 · Asset acquisition requirement

Wanted: operating solar assets, 20–100 MW AC, with long-term PPA

Any district in Rajasthan, Gujarat, Madhya Pradesh or Karnataka

An investor seeks operating ground-mounted solar plants, as single assets or portfolios, with at least ten years of PPA remaining with a central agency, state utility or investment-grade commercial buyer. Will take 100% or a controlling majority and can assume existing debt.

Buyer
Sample Energy Ventures Pvt Ltd (illustrative)
Capacity sought
20–100 MW AC per asset; portfolios up to 300 MW
Technology
Ground-mounted PV commissioned 2017 or later
Offtake
PPA with at least 10 years remaining; central agency, state utility or investment-grade commercial buyer
Stake
100% or controlling majority; existing debt can be assumed
Budget
Up to ₹600 crore enterprise value per transaction
Response time
Indicative offer within four weeks of data-room access
Reference checkedAt least one submitted project reference was independently contacted or validated, subject to the displayed scope.

Status: Open

Real listings show these facts only as the lister declares them, with the trust label stating what BARREL checked and when. Exact locations, documents and the other party's identity open after the NDA.